By Angela Agina
Kitui County – Director of Coordination at State House, Boniface Musambi, visited the Umaa Dam Water Supply Project in Kitui County as part of a development tour, accompanied by a section of elected leaders from the county.
Mr. Musambi was received at the project site by the Resident Engineer, Eng. Apphia Kaluku, who briefed the delegation on the progress of the project, key milestones achieved, and the challenges affecting its implementation.
The visit provided an opportunity for the delegation to assess the status of the project and appreciate the works being undertaken to advance the Government’s investment in water infrastructure for the people of Kitui County.
Construction of the Umaa Dam project commenced in 2009 but stalled in 2010, remaining inactive for approximately 14 years. The project was revived in 2024, with construction works recommencing in January of the same year.
The revival marked an important step towards completing the infrastructure and unlocking its intended benefits for Kitui Town and surrounding areas. The overall progress currently stands at 35 per cent under the new contract, while cumulative progress, including works undertaken under the previous contract, stands at 79.2 per cent.
Umaa Dam is a 33-metre-high zoned earth-fill dam comprising a central clay core, protective filters, shell material and upstream riprap. The dam has a non-overflow crest elevation of 1,163.4 metres above sea level, with a crest approximately 240 metres long and seven metres wide. The dam’s spillway, located on the right-hand abutment, comprises a 12-metre-long free-overflow ogee crest, a concrete chute and a stilling basin. Upon completion, the dam will impound approximately 1.2 million cubic metres of water and cover an area of approximately 12.4 hectares.
The project also includes associated water supply infrastructure. A 1.6-kilometre DN200 steel pipeline will convey treated water from the clear-water tank to the existing distribution tanks at Kwa Ngindu, on the outskirts of Kitui Town. Upon completion, the project is expected to provide water to Kitui Town and its environs, serving a population of more than 75,000 people.
The site visit also provided an opportunity for the delegation to review the project’s implementation status, identify challenges, and underscore the importance of completing the infrastructure to enhance water availability and support socio-economic development in the county.
Among the leaders accompanying the State House delegation were Nominated Senator Hon. Beth Syengo Kalunda, Kitui South MP Dr. Rachael Kaki Nyamai, Kitui East MP Hon. Nimrod Mbithuka Mbai, and Mwingi West MP Hon. Charles Ngusya Nguna, among others.
The engagement reflects the importance of continued coordination and oversight in advancing strategic government projects and ensuring that investments in water infrastructure deliver their intended benefits to communities.
The National Water Harvesting & Storage Authority (NWHSA) remains committed to implementing strategic water infrastructure that contributes to improved water availability, resilience and sustainable socio-economic development for communities across the country.
###


Leaders Signing Visitors Book


Photo of Site

Bonface Musambi & Elected Leaders

Contractor Briefing Leaders