The Authority has reaffirmed its commitment to fast-track the Muruny (Siyoi) Dam in West Pokot County, with the aim of completing the remaining works by 30th December 2026.
The commitment comes as the Principal Secretary, State Department for Water and Sanitation, Julius Korir urged the contractor to accelerate works by increasing shifts and undertaking day and night operations where necessary to ensure the project meets the set deadline.
The PS emphasized that the project is critical and called on the contractor to have no excuse relating to cash flow, urging all parties to focus on completion.
The PS also urged the project team to take advantage of the ongoing rainy season to impound water, noting that completion of the water treatment component will enable testing of the treatment works once the required water levels are attained.
Ag. CEO Eng. Julius Mugun reaffirmed the Authority’s commitment to accelerate the outstanding works.
The project has made significant progress, currently standing at 87.4% overall completion and 90.8% on the critical path. The cyclopean dam is 72.72% complete, while the 11.2km raw water pipeline is 98.5% complete.
Major components including the 180m spillway, 182m twin diversion culvert, intake tower footbridge, 71m reservoir bridge and 15m spillway bridge have been completed.
Located in Lelan Ward, Pokot South Constituency, the project is designed to provide domestic water to approximately 350,000 people serving Kapenguria and surrounding areas including Makutano, Paraywa, Kabichbich, Chepyomet, Kaibos, Siyoi, Chepararia, Pertum, Korelach, Kapkoris, Nasokal, Chewoyet, Keringet, Karas, Murkwijit and Kishaunet.
The project includes construction of a 30m-high dam designed to impound 8.9 million cubic metres of water, together with water treatment, storage, transmission and the pipeline.
NWHSA remains committed to delivering sustainable water infrastructure that will enhance water security and improve the livelihoods of communities in West Pokot and beyond.